Farm-Out Timeline

Activities Days
Publication and Posting of PNOC EC's invitation Day 0
Deadline for submission of Letter of Intent (LOI) Day 15 (Calendar Days)
Pre-Selection Conference Day 20
Due Diligence of Third Party-Participant upon submission of LOI and signing of Confidentiality Agreement Day 1 to 59
Deadline for submission of Eligibility Requirements and Proposals Day 60
Opening of submitted Eligibility Requirements and Proposals; Announcement of Complying Third-Party Participant Day 60
Evaluation of Technical and Financial Proposals Day 61 Day 67
Approval of the PNOC EC Board of Directors of the Winning Participant Within 15 Calendar Days
Transmittal of Notice of Award to the Winning Participant; PNOC EC and the Winning Participant finalize and agree on the Farm-in Agreement (FIA), Joint Operating Agreement (JOA) and Deed of Assignment (DA) Within 15 Calendar Days
Review of FIA, JOA, and DA by the Office of the Government Corporate Counsel (OGCC) Within 20 Working Days
Signing of FIA, JOA, and DA by PNOC EC and the Winning Participant; PNOC EC requests DOE's approval of the DA Within 10 Calendar Days
Evaluation and Approval of the DA by the DOE in accordance with DC2007-04-003 Within 21 Working Days

Projects and Operations

In line with PNOC EC's mandate of providing a stable energy supply for the Philippines, the company is also involved in the exploration, development and production of coal in the country.

PNOC Exploration Corporation’s presence in the Philippine petroleum industry spans over 30 years, with its role evolving from that of a catalyst and promoter of local petroleum exploration to that of

PNOC EC's Trading and Marketing business continue to serve the fuel requirements of its industrial customers with coal supply coming from its own COC 41 small scale mines and other indigenous sources.

Back to top